The exemption regulations have not been made yet. The dates below are the published timetable, not fixed law. We review this position on 17 December 2026. Read the full 2027 exemption timetable.

Compliance 8 November 2026

From waste exemption to permit: what changes

A site that has run on a waste exemption for years can find itself needing an environmental permit in 2027. The date depends on the code, and the paperwork does not stop at the permit: a permitted receiving site also comes into digital waste tracking.

The dates, the codes and the routes in one place are on the 2027 exemption guide. To see the status and the next step for your own code, use the free exemption checker.

Which codes become permits, and when

Thirteen exemptions are affected, and they fall into three groups. These dates are subject to parliamentary approval, and the reforms are expected to come into force on 6 January 2027.

Code What it covers Date What happens
T8 Mechanically treating end-of-life tyres 6 April 2027 Withdrawn. A permit is needed to continue, and continued operation applies while an application made before this date is processed.
T9 Recovering scrap metal 6 April 2027 Withdrawn. A permit is needed to continue, with the same continued operation for an application made before this date.
U16 Using depolluted end-of-life vehicles for parts 6 April 2027 Withdrawn. A permit is needed to continue, with the same continued operation for an application made before this date.
S3, T20, T21 The water industry codes 6 January 2027 Not withdrawn. The waste codes and descriptions change, so check the updated list before the next use.
T4, T6, T12, D7 Storing, preparing, treating wood and plant matter, manual treatment, burning plant waste 6 July 2027 Changing. The new conditions apply from this date, and a permit is needed if the site cannot meet them.
U1, S1, S2 Use in construction, storage in secure containers, storage at a secure site 6 January 2028 Changing. The new conditions apply from this date, and a permit is needed if the site cannot meet them.

A new permit, or a variation of the one you hold

There are two routes and they are not interchangeable.

Where the exempt activity is technically connected to a site that already has an environmental permit, the guidance says to bring the activity into that permit by variation, by 6 July 2027, or to stop. That is one application against a permit the site already holds. What technical connection means, and the questions that decide it, is covered in technical connection and waste exemptions.

Where the activity is not connected to a permitted site, the route for a withdrawn exemption is an application for a waste environmental permit before 6 April 2027. For T8, T9 and U16 only, the guidance allows the site to keep working under the exemption while that application is processed, provided it was made before 6 April 2027.

This page does not promise that a permit will be granted, and it does not set out an application route beyond what the published guidance says. The regulator decides the application on its merits.

What a permitted site then has to report

A site that becomes permitted becomes a permitted receiving site. That brings it into digital waste tracking, so every load received has to be recorded and submitted within two working days, counted from the day after the load arrives.

The rule that catches people out is the timing: the reporting duty starts when the permit does, not months later. Plan the tracking side at the same time as the permit application, not after it. See digital waste tracking software for what the duty covers and how a system files to the service.

The records to keep

Once the duty applies, each load needs a record with the waste description, the EWC code, the weight, the date and time of transfer, the carrier and the receiving site, and the signatures. Those records are the site's evidence, so they need somewhere durable rather than a folder of paper.

Two records often get confused. The site record is the permit and the load records the receiving site keeps. The carrier record is the permit or exemption, driver numbers, vehicles and documents for the business that moves the waste. The free carrier hub on waste carriers holds the second; the site register and the load records hold the first.

What to do now

  1. List every exemption registered at the site, and check each code against the table above.
  2. Answer the technical connection questions for the site, and write the reasoning down with the date.
  3. Decide the route: a variation of an existing permit, a new permit, or meeting the new conditions.
  4. Diary the apply-by date. For T8, T9 and U16 that is 6 April 2027; for a connected exemption brought into a permit, 6 July 2027.
  5. Plan the reporting side at the same time, so the first permitted load is also a properly reported load.

Sources and checked date

Sources: GOV.UK, Waste exemptions: new rules from January 2027; GOV.UK, Digital waste tracking: check if you need to report the waste you receive. Checked 8 November 2026. This is LoadLog's reading of published guidance, not legal advice, and the reforms are subject to parliamentary approval.