The exemption regulations have not been made yet. The dates below are the published timetable, not fixed law. We review this position on 17 December 2026. Read the full 2027 exemption timetable.
Waste exemption checker 2027
Pick your exemption code or your sector, answer four short questions about the site, and see the status, the date and the next step. Free, no account needed.
Step 1: your exemption
Step 2: is the exemption technically connected to a permitted site?
The Environment Agency says it is up to you to work out if you have a technical connection. These questions are a guide, not a determination.
All thirteen codes and dates
Every code the reforms affect, with its status and the date that applies. Subject to parliamentary approval.
| Code | Name | Status | Date |
|---|---|---|---|
| S3 | Storing sludge | Code and description change | 6 January 2027 |
| T20 | Treating waste at a water treatment works | Code and description change | 6 January 2027 |
| T21 | Recovering waste at waste water treatment works | Code and description change | 6 January 2027 |
| T8 | Mechanically treating end-of-life tyres | Withdrawn | 6 April 2027 |
| T9 | Recovering scrap metal | Withdrawn | 6 April 2027 |
| U16 | Using depolluted end-of-life vehicles for parts | Withdrawn | 6 April 2027 |
| T4 | Storing and preparing for further treatment | Changing | 6 July 2027 |
| T6 | Treating waste wood and waste plant matter | Changing | 6 July 2027 |
| T12 | Manually treating waste | Changing | 6 July 2027 |
| D7 | Burning plant and untreated wood waste where it is produced | Changing | 6 July 2027 |
| U1 | Use of waste in construction | Changing | 6 January 2028 |
| S1 | Storing waste in secure containers | Changing | 6 January 2028 |
| S2 | Storing waste at a secure site | Changing | 6 January 2028 |
Checked 7 November 2026. Source: GOV.UK, waste exemptions: new rules from January 2027. Subject to parliamentary approval.
Questions about the checker
What is a waste exemption checker?
A free tool that shows what the 2027 reforms do to a waste exemption code: whether it is withdrawn, changing, or has a code and description change, the date that applies and the next step.
Does the checker decide whether my exemption is technically connected?
No. The Environment Agency says it is up to the operator to work out whether a technical connection exists. The four questions give an indicative view only. They are not a legal determination, and the operator must decide.
Do I need an account to use the checker?
No. The checker runs in the browser with no account, no email and no card. Nothing you answer is sent to us.
Which exemption codes does the checker cover?
T8, T9, U16, T4, T6, T12, D7, U1, S1, S2, S3, T20 and T21. Those are the thirteen codes affected by the 2027 reforms in England.
For the full timetable and what it means by sector, see waste exemption reform 2027.